Question: Using the values within the following table, calculate the early finish of activity D. A. 10 B. 12 C. 13 D. 15 Activity Name A

Using the values within the following table, calculate the early finish of activity D.Activity Name A B Successor B, C Duration 5 D 2 C

A. 10 B. 12 C. 13 D. 15

Activity Name A B Successor B, C Duration 5 D 2 C D, E 4 D F 4 E F 6 F None 6