Question: Using the values within the following table, calculate the late start of activity C. A. 6 B. 9 C. 4 D. 8 Activity Name Successor
Using the values within the following table, calculate the late start of activity C.
A. 6 B. 9 C. 4 D. 8
Activity Name Successor Duration A B, C 5 B D 2 C D, E 4 D F 4 E F 6 F None 6