Question: While identifying risks for a new construction project, you discover that a chemical you are using on your building cannot be applied in rainy conditions.
While identifying risks for a new construction project, you discover that a chemical you are using on your building cannot be applied in rainy conditions. You also learn that your project will be ready for the chemical application around the time when most of the rainfall happens in this part of the country. Since the project can’t be delayed until after the rainy season and you need to make sure the building gets the chemical coating, you decide that your team will just have to allow enough time in the schedule for nonworked rain days.
This is an example of which strategy?
A. Mitigate B. Exploit C. Accept D. Transfer