Question: You are a project manager working on a project involving a new scientific discovery in conjunction with your local university. Because of some changes that
You are a project manager working on a project involving a new scientific discovery in conjunction with your local university. Because of some changes that were approved during the Monitoring and Controlling processes, you discover that the descriptions of the deliverables that make up the final product of the project are no longer accurate or complete. Which of the following will you use to track the changes to the deliverables and ensure their descriptions are accurate and complete, and what process is this associated with?
A. Scope change control system in Control Scope B. Quality control system in Control Quality C. Configuration management system in Perform Integrated Change Control D. Change control system in Monitor Communications