Question: The project manager has just determined that three functional managers with a high interest in the project hold a particularly high degree of influence in
The project manager has just determined that three functional managers with a high interest in the project hold a particularly high degree of influence in the allocation of enterprise resources. Armed with this new information, she updates her salience model and considers how it impacts the project. In what activity is the project manager engaged?
A. Stakeholder analysis B. Resource analysis C. Stakeholder engagement D. Stakeholder monitoring