Question: You are a project manager working on contract for an upscale retail toy store. Your project involves implementing a Party Event Planner department in stores
You are a project manager working on contract for an upscale retail toy store. Your project involves implementing a Party Event Planner department in stores in 12 locations across the country as a pilot to determine whether this will be a profitable new service all the stores should offer. You’ve identified two alternative methods of implementing the pilot. Alternative A’s initial investment equals $598,000. The PV of the expected cash inflows is $300,000 in year 1 and $300,000 in year