Question: You are developing the cost baseline and the project budget. You know that all of the following are true regarding these two elements except for

You are developing the cost baseline and the project budget. You know that all of the following are true regarding these two elements except for which one?

A. The project budget includes management reserves.

B. Work package estimates and contingency reserves are included in the cost baseline and project budget.

C. The cost baseline includes the project budget.

D. Activity cost estimates and contingency reserves are included in the cost baseline and project budget.