Question: You are managing a project with AC = $25,100, ETC = $45,600, VAC = -$2,600, BAC = $90,000, and EAC = $92,100. Your sponsor asks

You are managing a project with AC = $25,100, ETC = $45,600, VAC = -$2,600, BAC =

$90,000, and EAC = $92,100. Your sponsor asks you to forecast how much money you expect to spend on the remainder of the project. Which is the BEST estimate to use for this forecast?

A. $45,600 B. $87,400 C. $90,000 D. $92,100