Question: You are the project manager for a project that will produce a mobile phone application that sends alerts when the UV rays are at dangerous
You are the project manager for a project that will produce a mobile phone application that sends alerts when the UV rays are at dangerous levels, alerting users to stay indoors.
As you move into the final closing stages of the project, you review communications generated for and by stakeholders as a method of analyzing feedback. What document will you reference to review this feedback?
A. Change log B. Lessons learned register C. Project communications D. Quality reports