Question: You are the project manager for a project that will produce a mobile phone application that sends alerts when UV rays are at dangerous levels,

You are the project manager for a project that will produce a mobile phone application that sends alerts when UV rays are at dangerous levels, alerting users to stay indoors.

You are in the process of measuring schedule performance against the schedule baseline.

Within a predictive life cycle, what process group are these activities associated with?

A. Initiating B. Planning C. Executing D. Monitoring and Controlling