Question: You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. Which
You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. Which of the following is the BEST metric to use for forecasting?
A. EV and AC B. SV and CV C. ETC and VAC D. SPI and CPI