Question: You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. The

You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $80,000 and CPI of .95. The project has spent

$25,000 of its budget so far. How much more money do you plan to spend on the project?

A. $59,210 B. $80,000 C. $84,210 D. $109,210