Question: You are using a control chart to analyze defects, when something on the chart causes you to realize that you have a serious quality problem.

You are using a control chart to analyze defects, when something on the chart causes you to realize that you have a serious quality problem. What is the MOST likely reason for this?

A. The rule of seven B. Upper control limits C. Lower control limits D. Plan-Do-Check-Act