Question: You have just started work on the Project Scope Statement. You are analyzing the expected deliverables, when you discover that one of them could be
You have just started work on the Project Scope Statement. You are analyzing the expected deliverables, when you discover that one of them could be delivered in three different ways. You select the best method for creating that deliverable. What is the BEST way to describe what you are doing?
A. Alternatives Analysis B. Decomposition C. Define Scope D. Stakeholder Analysis