You’re the project manager on a software project. Your team has only completed half of the work, when the sponsor informs you that the project has been terminated. What is the BEST action for you to take?
A. Verify the deliverables produced by the team against the scope, and document any place they do not match B. Call a team meeting to figure out how to spend the rest of the budget C. Work with the sponsor to see if there is any way to bring the project back D. Tell the team to stop working immediately