Question: Youre a project manager on a software project. Your team is busy executing the project and creating the deliverables, but there have been several changes

You’re a project manager on a software project. Your team is busy executing the project and creating the deliverables, but there have been several changes requested by stakeholders over the past few weeks. Each time you got one of these changes, you called a meeting with your team and the stakeholders to discuss it. Why did you do this?

A. Every change needs to be evaluated by a change control board B. You’re delegating the work of evaluating changes C. You do not have a good change control system in place D. You are using a work authorization system to assign the work

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!