Question: A critical path activity has ___________________ float during the planning process. a. the most b. zero c. negative d. positive
A critical path activity has ___________________ float during the planning process.
a. the most
b. zero
c. negative
d. positive
Step by Step Solution
3.37 Rating (147 Votes )
There are 3 Steps involved in it
A critical path activity has zero float during the planning process The critical path i... View full answer