Question: Adding to the project after it has already begun without making adjustments to time, cost, or resources is known as: a. scope creep b. risk
Adding to the project after it has already begun without making adjustments to time, cost, or resources is known as:
a. scope creep
b. risk
c. milestones
d. acceptance criteria
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
a scope creep Adding to the project after it has already begun without making adjustments ... View full answer