Question: Adding to the project after it has already begun without making adjustments to time, cost, or resources is known as: a. scope creep b. risk

Adding to the project after it has already begun without making adjustments to time, cost, or resources is known as:

a. scope creep

b. risk

c. milestones

d. acceptance criteria

Step by Step Solution

3.45 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a scope creep Adding to the project after it has already begun without making adjustments ... View full answer