Question: During WBS creation on a large, complex project, the product and project deliverables are broken down into progressively lower levels of detail. Once the WBS
During WBS creation on a large, complex project, the product and project deliverables are broken down into progressively lower levels of detail.
Once the WBS has been defined at the second or third level of detail, whose input is essential in order to break down the work further?
a. sponsor
b. subject matter experts
c. internal stakeholders
d. external stakeholders
Step by Step Solution
★★★★★
3.32 Rating (155 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
b subject matter experts Subject matter experts possess the ... View full answer