While all projects use _______________ risk analysis, _______________ risk analysis is used only when it is needed
Question:
While all projects use _______________ risk analysis, _______________ risk analysis is used only when it is needed and there is sufficient data to develop appropriate models.
a. quantitative, qualitative
b. quantitative, opportunity
c. opportunity, qualitative
d. qualitative, quantitative