Question: While all projects use _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ risk
While all projects use risk analysis, risk analysis is used only when it is needed and there is sufficient data to develop appropriate models.
a quantitative; qualitative
b quantitative; opportunity
c opportunity; qualitative
d qualitative; quantitative