(a) Paid for supply at the kiln site for 30 lakh first class bricks @ Rs. 30 per 1,000.
(b) Paid for supply at the kiln site for 60 lakh second class bricks @ Rs. 25 per 1,000.
(c) Paid carriage charges for carrying all bricks from kiln to store yard @ Rs. 1.50 per 1,000.
(d) Paid unloading charges Rs. 90 (lump sum).
(e) Paid for stacking in the store yard Rs. 180 (lump sum).
(f) Breakage in handling: 1% for first class bricks, 2% for second class bricks.