Question: Processing times (including setup times) for five jobs that arrived today and are waiting to be processed in the same order on three machines in

Processing times (including setup times) for five jobs that arrived today and are waiting to be processed in the same order on three machines in a shop are given below. Determine the sequence of jobs that will likely minimize the make-span.

Processing Time (hours) Job Machine 1 Machine 2 Machine 3 A 6 3 B 3 5. 4 2 3. 6 D. 3 4 E 2 2