Question: Processing times (including setup times) for five jobs that arrived today and are waiting to be processed in the same order on three machines in
Processing times (including setup times) for five jobs that arrived today and are waiting to be processed in the same order on three machines in a shop are given below. Determine the sequence of jobs that will likely minimize the make-span.

Processing Time (hours) Job Machine 1 Machine 2 Machine 3 A 6 3 B 3 5. 4 2 3. 6 D. 3 4 E 2 2
Step by Step Solution
★★★★★
3.41 Rating (157 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Surrogate problem 1 Processing Time hours Job Machine 1 Machine 2 A 4 3 B 3 4 C ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
