Question: Jamison Construction has implemented a cost estimation system using regression analysis. The variable cost per hour of labor is $35 and the fixed cost was
Jamison Construction has implemented a cost estimation system using regression analysis. The variable cost per hour of labor is $35 and the fixed cost was determined to be $125,000. If Jamison projects it will be working 200,000 hours in 2019, what is the projected total cost?
Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
Total Cost 200000 35 125000 7000000 ... View full answer