Question: Jamison Construction has implemented a cost estimation system using regression analysis. The variable cost per hour of labor is $26 and the fixed cost was

Jamison Construction has implemented a cost estimation system using regression analysis. The variable cost per hour of labor is $26 and the fixed cost was determined to be $254,000. If Jamison projects it will be working 296,000 hours in 2016, what is the projected total cost? Total cost