Question: A technique that calculates multiple project durations with different sets of activity assumptions and variables is: Process Analysis Theoretical Analysis Simulation Effect Analysis
A technique that calculates multiple project durations with different sets of activity assumptions and variables is:
Process Analysis Theoretical Analysis Simulation Effect Analysis