Question: An activity has 3 estimates, provided below: Optimistic = 10 days Pessimistic = 25 days Realistic - 15 days What is the three point estimate
An activity has 3 estimates, provided below:
Optimistic = 10 days Pessimistic = 25 days Realistic - 15 days What is the three point estimate for this activity?