Question: An activity has 3 estimates, provided below: Optimistic = 10 days Pessimistic = 25 days Realistic = 15 days What is the beta distribution estimate
An activity has 3 estimates, provided below:
Optimistic = 10 days Pessimistic = 25 days Realistic = 15 days What is the beta distribution estimate for this activity?