Question: An activity has 3 estimates, provided below: Optimistic = 10 days Pessimistic = 25 days Realistic = 15 days What is the beta distribution estimate

An activity has 3 estimates, provided below:

Optimistic = 10 days Pessimistic = 25 days Realistic = 15 days What is the beta distribution estimate for this activity?

16 60A 3 7 3 B C D 5 9 E F

16 60A 3 7 3 B C D 5 9 E F Start 2 69 G K 10 10 I Finish