Question: . As a project manager, you determine that you do not have a need to purchase anything for your project. With that decision, which processes
. As a project manager, you determine that you do not have a need to purchase anything for your project.
With that decision, which processes will not be performed on your project?
a) Plan contracting and communications planning
b) Quality assurance and select sellers
c) Request seller responses and risk identification
d) Plan contracting, request seller responses and select sellers