Question: If the CPI is 0.1, this indicates: A. The project is performing extremely poorly on cost. B. The project is costing 10% over what was
If the CPI is 0.1, this indicates:
A. The project is performing extremely poorly on cost.
B. The project is costing 10% over what was expected.
C. The project is only costing 90% of what was expected.
D. The project is performing extremely well on cost.