Question: If the CPI is 0.1, this indicates: A. The project is performing extremely poorly on cost. B. The project is costing 10% over what was

If the CPI is 0.1, this indicates:

A. The project is performing extremely poorly on cost.

B. The project is costing 10% over what was expected.

C. The project is only costing 90% of what was expected.

D. The project is performing extremely well on cost.