Question: If there are multiple critical paths on the project, which of the following must also be true? A. Only one path will ultimately emerge as
If there are multiple critical paths on the project, which of the following must also be true?
A. Only one path will ultimately emerge as the true critical path.
B. The schedule risk will be higher with multiple critical paths than with one.
C. The schedule should be crashed in order to resolve the conflict.
D. 'The schedule should be fast-tracked in order to resolve the conflict.