Question: If there are multiple critical paths on the project, which of the following must be true? Group of answer choices Schedule risk will be higher
If there are multiple critical paths on the project, which of the following must be true? Group of answer choices Schedule risk will be higher with multiple critical paths than with one. Only one path will ultimately emerge as the true critical path. The schedule should be lengthened to resolve the conflict. The schedule should be shortened to resolve the conflict