Question: If you were creating duration estimates for a schedule activity, which of the following tools or techniques would NOT be appropriate to use? A. Expert

If you were creating duration estimates for a schedule activity, which of the following tools or techniques would NOT be appropriate to use?

A. Expert judgment.

B. Reserveanalysis.

C. 'Three-point estimating.

D. Least-squares estimating.