Question: John, a project manager for Code Crashers, Inc., has a project with a group of inexperienced programmers that will develop a software package that creates
John, a project manager for Code Crashers, Inc., has a project with a group of inexperienced programmers that will develop a software package that creates Material Safety Data Sheets (MSDS) for a chemical company. This situation strongly resembles a project his colleague, Peter, worked on in 2006. If John needs to come up with a rough order of magnitude estimate, what tool or technique should he use?
Parametric Estimating Bottom Up Estimating Three-point estimate Analogous Estimating