Question: . Significant changes occurring throughout the project life cycle can trigger: a) A rewrite of the project charter b) The need to revisit one or
. Significant changes occurring throughout the project life cycle can trigger:
a) A rewrite of the project charter
b) The need to revisit one or more of the planning processes or some of the initiating processes
c) Assignment of a new project manager
d) Cancellation of the project