Question: The activity duration estimates should be developed by: A. 'The person or team doing the work. B. The project manager. C. Senior management. D. The

The activity duration estimates should be developed by:

A. 'The person or team doing the work.

B. The project manager.

C. Senior management.

D. The customer.