Question: Your team is hard at work on their assigned project tasks when one team member discovers a risk that was not identified during risk planning.
Your team is hard at work on their assigned project tasks when one team member discovers a risk that was not identified during risk planning.
What is the FIRST thing to do?
A. Halt work on the project.
B. Update the risk management plan.
C. Look for ways to mitigate the risk.
D. Assess the risk.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
