Question: When changes are approved and made to the project, they should be: A. Tracked against the project baseline. B. Incorporated into the project baseline. C.
When changes are approved and made to the project, they should be:
A. Tracked against the project baseline.
B. Incorporated into the project baseline.
C. Included as an addendum to the project plan.
D. Approved by someone other than the project manager.