Question: owing best describes when a project baseline should be changed? Group of answer choices A project baseline should be changed when a cost increase occurs.
owing best describes when a project baseline should be changed? Group of answer choices A project baseline should be changed when a cost increase occurs. A project baseline should be changed when a change to cost, schedule, or scope is approved. A project baseline should be changed when a major delay occurs. Changes should never be made to a project baseline