Question: While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this
While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called?
Start-to-Finish Start-to-Start Finish-to-Start Finish-to-Finish