Question: While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this
While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called?
A. Start-to-Finish B. Start-to-Start C. Finish-to-Start D. Finish-to-Finish
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
