Question: While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this


While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called?

A. Start-to-Finish B. Start-to-Start C. Finish-to-Start D. Finish-to-Finish