Question: You are managing a project that has a task to translate several pages of a document into Spanish. This is similar to a project done
You are managing a project that has a task to translate several pages of a document into Spanish. This is similar to a project done last year when a document was translated into German. You are not sure how long it will take to translate into Spanish, so you look at the project plan from the German translation and use that activity duration for your current project. What type of estimating is this an example of?
Hypothesis Parametric Estimating Analogous Estimating What-if Scenario Analysis