Question: You are managing a project that has a task to translate several pages of a document into Spanish. This is very similar to a project


You are managing a project that has a task to translate several pages of a document into Spanish. This is very similar to a project done last year where a document was translated into German. You are not sure how long it will take to translate into Spanish so you look at the project plan from the German translation and use the activity duration for your current project What type of estimating is this an example of?
A. Hypothesis B. Parametric Estimating C. Analogous Estimating D. What if Scenario Analysis