Question: You are working on a project to construct an office building in another country when you discover that you must obtain a second building permit
You are working on a project to construct an office building in another country when you discover that you must obtain a second building permit from the local authority. When you inquire about this, you find out that the local permit will take 6 to 8 weeks to be issued; however, an official mentions that you can speed this up by paying a $500 "rush fee". 'The fee is within the project's budget, and the need is urgent. What is the BEST thing to do?
A. Pay the $500.
B. Do not pay the $500 and wait the 6 to 8 weeks.
C. Ask the official if he would accept less than $500.
D. Ask someone on your team to pay the fee for you.