Question: You recently took over a project as the project manager. This is your first project management assignment. The project sponsor is very supportive and is
You recently took over a project as the project manager. This is your first project management assignment. The project sponsor is very supportive and is helping you out in successfully managing the project.
Recently, some bad quality deliverables were received on the project, and the project sponsor suggested that you to periodically review the vendor’s progress to deliver project scope and quality, within cost and on schedule, as compared to the contract. Which of the following statements is true in this context?
The sponsor has asked you to carry out regular trend analysis.
The sponsor has asked you something that is not a good project management practice.
The sponsor has asked you to carry out regular procurement performance reviews.
The sponsor is giving you a bigger workload so that you can perform better on the next assignment.