Question: . Your project has fallen behind schedule and you are trying to get it back on track so you decide to crash some tasks. You
. Your project has fallen behind schedule and you are trying to get it back on track so you decide to crash some tasks. You will be most successful in completing the project on time and within budget by:
a) Asking the customer which tasks could be crashed
b) Crashing all tasks that are estimated to take more than 5 days
c) Evaluating the risk impact of crashing tasks on the critical path
d) Evaluating the cost and risk impact of crashing tasks with one or more days of float