Question: . Resource leveling shifts tasks within their slack allowances in order to minimize the period variations in resource use. It often results in: a) Project
. Resource leveling shifts tasks within their slack allowances in order to minimize the period variations in resource use. It often results in:
a) Project duration that is longer than the preliminary schedule
b) Project duration that is shorter than the preliminary schedule
c) No change to the project duration as the critical path is unchanged
d) Fast tracking