What is the labor price variance? a. 62,250 favorable b. 72,625 unfavorable c. 134,875 favorable d. 10,375

Question:

What is the labor price variance?
a. €62,250 favorable 

b. €72,625 unfavorable
c. €134,875 favorable 

d. €10,375 unfavorable

The following data relate to the budget and actual results of Oscar Enterprises, which produces and sells net balls in France.

The standard cost of €15.00 per a net ball is as follows:

During the month of December, 55,000 kgs and 41,500 labor hours were used.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Horngrens Cost Accounting A Managerial Emphasis

ISBN: 9780135628478

17th Edition

Authors: Srikant M. Datar, Madhav V. Rajan

Question Posted: