Complete the following table. Lead time for the part is 2 weeks. The lot size is 100. What is the projected available at the end of week 3? When is it planned to release an order? Week Gross Requirements Scheduled Receipts Projected Available 30 Net Requirements Planned Order Receipt Planned Order Release 1 20 2 65 100 3 35 4
Chapter 4, Problems #6
Complete the following table. Lead time for the part is 2 weeks. The lot size is 100. What is the projected available at the end of week 3? When is it planned to release an order?
This problem has been solved!
Do you need an answer to a question different from the above? Ask your question!
Related Book For
Introduction To Materials Management
8th edition
Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen
ISBN: 978-9386873248