The Acme Widget Company makes widgets in two models, and the bottleneck operation is in work center

Question:

The Acme Widget Company makes widgets in two models, and the bottleneck operation is in work center 10. Following is the resource bill (in hours per part).

Hours per Part Work Center Model A Model B 10 2.4 3.5


The master production schedule for the next 5 weeks is

3 4. Week Model A 50 60 48 70 50 Model B 20 40 55 30 45 2.


a. Using the resource bill and the master production schedule, calculate the number of hours required in work center 10 for each of the 5 weeks. Use the following table to record the required capacity on the work center.


b. If the available capacity at work station 10 is 260 hours per week, suggest possible ways of meeting the demand in week 3.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Introduction To Materials Management

ISBN: 978-9386873248

8th edition

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

Question Posted: